24 men can do a work in 14 days by working 6 hours a day. If the work is to be completed in 8 days by working 7 hours per day how many men are required?
Correct option is (A) 27
Given that 36 men can built a wall in 12 days.
\(\therefore\) Total work = 36 \(\times\) 12
Let 16 men can built the wall in x days.
\(\therefore\) Total work = 16 \(\times\) x
\(\because\) Both work...
Correct option is (B) 36
Total work done by 24 men in 14 days by working 6 hours a day \(=24\times14\times6\)
Let x men are required to complete same work in 8 days...